60 Questions

Which is a purpose of the risk management approach?
Which process provides an interface with corporate or programme management?
Which is a minimum requirement for applying the organization theme?
How is the 'manage by exception' principle applied?
Which management product should always be updated when a product fails its quality check?
Which is a purpose of an Issue Report?
On which environment is PRINCE2 based?
What is the trigger for the Starting up a Project process?
Which is a purpose of the quality theme?
Which statements apply to a stage plan? 1. It is produced for the project during the 'initiating a project' process 2. It is produced close to the time when the planned events will take place 3. It provides the basis for day-to-day control by the project manager 4. It provides the basis for control by the project board
Identify the missing words in the following sentence. If a baselined product requires modification, the recommended [ ? ] procedure, or equivalent procedure should be used.
What should be provided by a project mandate?
Which process aims to ensure that during the project all parties understand the project objectives?
Which role is responsible for the management of a risk assigned to it?
Which is a purpose of the organization theme?
Which is a minimum requirement for applying the business case theme?
What is likely to be avoided by applying the 'tailor to suit the project' principle?
Which is a purpose of a risk budget?
Which roles CANNOT be combined with the role of project assurance? 1. Project manager 2. Project support 3. Senior user 4. Executive
What is an advantage of applying the 'learn from experience' principle?
Which activity can take place within the 'managing a stage boundary' process?
Which describes the 'implement' step within the recommended risk management procedure?
Which aspect of project performance must be managed in order to have a clear understanding of what the project is to deliver?
What does applying the 'manage by stages' principle ensure?
Which is a purpose of the Risk theme?
Which principle is being applied when a project product description is produced?
What makes a project a PRINCE2 project?
What is a risk cause?
Which is an objective of the Starting up a Project process?
Which defines the sequence in which the project's products should be developed?
Which statement about the project support role is CORRECT?
If a work package is forecast to exceed its tolerances, how should a team manager inform the project manager?
Which is assumed to be the customer's responsibility in the PRINCE2 customer/supplier environment?
Which statement applies to Stage Plans?
Which is a minimum requirement for applying the organization theme?
What is established within the Initiating a Project process?
Which two statements describe a highlight report? 1. It provides a summary of the stage status 2. It is used by the project board to monitor the progress of the stage and project 3. It is produced by the project manager when a new risk is identified . 4. It is used by the project manager to escalate an exception
What must be recorded in the quality management approach, as a minimum requirement for applying the quality theme?
Which role is part of the project management team?
Which product forms the 'contract' between the Project Manager and the Project Board for the project?
In which situation might the Controlling a Stage process be used?
Which is a benefit of using PRINCE2?
Which statement correctly describes project assurance and quality assurance?
Which is a feature of PRINCE2?
What is an Exception Report used for during the Managing a Stage Boundary process?
What does the 'initiating a project' process provide?
What should be provided by corporate, programme management or customer before the 'starting up a project' process commences?
Identify the missing words in the following sentence. The six aspects of project performance to be managed are [ ? ], costs, timescales and scope.
Which is a responsibility of the managing level within the project management team?
Which two statements about tailoring are CORRECT? 1. Processes can be simplified or carried out in more detail. 2. Terminology can be changed to suit organizational standards. 3. Themes that are not relevant to the project can be excluded. 4. Project management team members can carry out any combination of roles.
Which is a purpose of an End Stage Report?
What must the project board do, as a minimum requirement for applying the change theme?
Which is a task of 'defining and analyzing products'?
Which statement about project stakeholders is CORRECT?
Which theme establishes mechanisms to monitor and compare actual achievements against planned achievements?
Which is a purpose of the benefits management approach?
Which process provides the project board with the information it requires in order to commit resources to the project?
Which product summarizes progress and is used to decide whether to continue with the project?
Which statement about management stages is CORRECT?
Which statement about acceptance criteria is CORRECT?
60 Questions
{{userScore}} / {{maxScore}}
{{title}}
{{image}}
{{content}}